Clark suing Miami Beach for $90 million over convention center contract | Dump Trucks Charlotte NC
Columbus Ohio Dump Truck Company Brief:
- Clark Construction Group is suing the city of Miami Beach for $90 million, which represents money the contractor says it is still owed under its contract for the $600 million, 1.5 million-square-foot renovation and expansion of the Miami Beach Convention Center.
Dump Trucks Columbus OH Insight:
Clark's allegations include claiming the city refused to pay for changes, didn't reimburse Clark or its subcontractors for delays related to 2017's Hurricane Irma, refused to grant appropriate extensions of contract time and unreasonably held retainage.
Specific allegations that Clark has made include:
- The city hired one of Clark's subcontractors to perform extra columbus oh dump truck company at the convention center and then made the decision to use part of Clark's earned fee to pay the subcontractor.
- The city continually changed what it required for Clark to obtain a Temporary Certificate of Occupancy.
- The city received enough money from the county and city to reimburse columbus oh dump truck company for hurricane costs but kept some of that money instead.
"Clark and its subcontractors proceeded with all columbus oh dump truck company in good faith to ensure absolutely no disruption to the city’s more than 92 planned, revenue-generating convention center shows, including four Art Basel Miami Beach events," said attorney Etan Mark, with the law firm of Mark Migdal & Hayden, in an emailed statement sent to Construction Dive on behalf of Clark.
"After attempting to reach resolution for more than one year, Clark is very disappointed to arrive at this juncture but must take this necessary step to protect itself and its subcontractors, many of which are local. The completion of the convention center is a point of pride for Clark and the residents of the city, and we look forward to a swift resolution so that Clark and its subcontractors can finally be paid for their hard work," the statement said.
Construction Dive reached out to Hill for comments about the lawsuit but has not yet received a response. However, in a media statement, Jimmy Morales, city manager, said, “I find it shocking, given that Clark Construction has delayed this project for nearly 1.5 years and has yet to finish, that they have the gall to file a lawsuit against us. Frankly, the city is the one entitled to damages, not Clark. We are not going to litigate this through the newspapers, and look forward to our day in court.”