Work halted on part of $9B Honolulu rail project due to incomplete design | Dump Trucks Charlotte NC

  • Kahikina also said the project is $2 billion to $3 billion over budget, and she let go expensive consultants that created redundancies and inefficiencies while reviewing project expenses. 
  • HART will likely alter the project's guideway path to avoid utilities that would otherwisehave to be moved. The new plan will require approval from landowners, including local schools and the University of Hawaii, and require buying more land.

Dump Trucks Columbus OH Insight:

The lack of plans created a situation where money was being spent, but no columbus oh dump truck company was getting done, Kahikina said: “You need to have the complete in order to go to the city to obtain permits before you can start work, so you’re just paying a contractor to be on standby.” 

She added that cutting the consultants was the start of eliminating waste, saying HART needed to “tighten our belt internally.” The project's operating cost is about $12 million per month, she said.

On the plus side, the new COVID-19 relief package signed by President Joe Biden earmarks $70 million to help cover losses on the rail project due to the pandemic. Declining tax revenue led the rail system to lose $62 million, according to Honolulu Civil Beat and HART is forecasting a total COVID-19-related loss of $76 million over the life of the project.

Thelast leg of the 20-mile Honolulu high-speed rail project was planned as a public-private partnership, although in November, HART announced the procurement process was canceled. In December, HART revealed details about the bids that made the project too expensive. The agency set the project’s design and construction "affordability limit" at $1.7 billion, but received bids from City Center Connection Group and Imua Transit Honolulu for $2.8 and $2.7 billion, respectively. Bids for operations and maintenance were also above set limits.

Kahikina said she hopes to turn over part of the route's operation by year end, but it will be up to the city’s Department of Transportation Services and Honolulu Mayor Rick Blangiardi to choose the exact timing.

Despite the pandemic, Hawaii construction overall remains strong, as evidenced by slight growth in construction jobs from March 2020 (an estimated 37,800) to December 2020 (an estimated 37,900). By comparison, hotel and restaurant jobs dropped from 112,200 to 70,000 in the same time period and dipped as low as 43,500 in May, according to the Honolulu Civil Beat.

Moving forward as the economy continues to rebound from the pandemic, private-sector projects are expected to contribute $10 billion in construction statewide, according to Cheryl Walthall, executive director of the General Contractors Association of Hawaii. In addition, $1.1 billion in state capital improvements are projected for the next year, along with another $1.1 billion in federal funds earmarked for transportation projects to improve and upgrade airports and harbors. 

Military spending also buoys the economy in Hawaii, Walthall said, and it is the second largest contributor to the local economy, behind tourism. Roughly $2.3 billion in U.S. Department of Defense spending is allocated for Hawaii every year, and a large chunk of that ends up going to local construction companies.

Editors' picks

  • story image
    Image attribution tooltip
    Permission granted by SFMTA

    2021 construction projects to watch

    Several high-profile jobs are scheduled for completion or are set to hit major milestones soon. Here are some that are sure to make headlines this year.

    By Kim Slowey • Jan. 05, 2021
  • Top OSHA fines of Q4 2020 include citations for 4 deaths

    The largest proposed fine for last quarter, which involved a fatal concrete mixer accident in Ohio, was for $451,079.

    By Kim Slowey • Jan. 27, 2021