Diadon Enterprises © 2018

The Dotted Line: Lessons from the Maryland Purple Line's amended contract | Dump Trucks Charlotte NC

An article fromsite logo
Published March 29, 2022
Joe Bousquin's headshot
Senior Reporter
Danielle Ternes/Construction Dive

This feature is a part of "The Dotted Line" series, which takes an in-depth look at the complex legal landscape of the construction industry. To view the entire series, click here.

Maryland's much-delayed Purple Line is getting a contractual do-over.

The Maryland Board of Public Works approved a modified agreement in January to tap Dragados USA and OHL USA, the American subsidiaries of two major Spanish construction firms, as the new design-build consortium on the project.

Construction attorneys say the modified public-private partnership (P3) agreement has the potential to set precedent for other closely watched public works projects, particularly as funds from the $1.2 trillion Infrastructure Investment and Jobs Act flow to the states.

Mark Himmelstein
Courtesy of Newmeyer Dillion
 

"This is the type of project that everyone in the business is aware of," said Mark Himmelstein, a partner in the Newport Beach, California, office of Newmeyer Dillion. "Lawyers will hold panels about what went wrong, and how to prevent that from happening in the future."

The Purple Line's new path

Operating as Maryland Transit Solutions (MTS), Dragados and OHL will now take over where Purple Line Transit Constructors, the light rail project's original contractors, walked away after an acrimonious and public dispute about cost overruns and time delays.

That group, made up of Fluor, Lane Construction and Traylor Bros., took the highly unusual step of quitting the infrastructure job before it was complete. A Maryland judge allowed the group to exit the deal in late 2020, pointing to "clear, direct and absolute" contract language that gave it the right to walk if a dispute lingered more than a year, which it had.

In announcing the modified agreement with MTS, the Maryland Department of Transportation emphasized that language had changed.

While MDOT hasn't made the new contract publicly available yet, in a release it said the original P3 agreement was modified to remove the right to unconditionally terminate for extended delay. The ability to conditionally terminate for extended delay was also narrowed.  

"The contractor can conditionally elect to terminate in the case of an extended force majeure event that is out of the control of either party, such as war, an act of terrorism, fire and flood, but that is not a unilateral right and the owner can elect to continue in that event," the release said.

The new agreement also added an additional $1.4 billion to the cost of the project, with an estimated completion date of 2026. The new price tag of $9.3 billion is 66% higher than the original $5.6 billion contract from 2016, and the project is more than four years behind schedule.

While the modified agreement breathes new life into the Purple Line, and keeps a project going that Maryland officials can't afford to get derailed again, construction attorneys say it's the original pact that was unusual. In giving the contractor the right to walk, particularly in the context of a public works project, it stood out.  

Randy Heller
Courtesy of Gallet Dreyer & Berkey, LLP
 

"A contractor would virtually never have the right to stop work, with the exception of nonpayment," said Randy Heller, a partner at Gallet Dreyer & Berkey in New York. "Any heavy duty contract would have a clause that specifically says no matter what happens, no matter what the dispute, finishing the job is so important that you may not stop columbus oh dump truck company for any reason."

The P3 exception to the rule

The wrinkle for the Purple Line is that it's being built as a P3. In these types of agreements, private entities agree to take on a part of the cost associated with building a public works project, in return for a piece of the revenues it generates. For example, Purple Line Transit Partners, the umbrella group that holds the concessionaire contract on the project, will operate and maintain the 16.2-mile, 21-station line for 30 years.

But in order to get private enterprises to assume that risk, P3 contracts are often less onerous than straight public works agreements, where the government entity unilaterally calls the shots.

"You can't as easily ram your contract down their throat," said Heller about P3 agreements. "Now the columbus oh dump truck company get to sit at the table and negotiate. And obviously, one of the conditions on the first agreement was the ability to walk away if things really went south."

The challenge of megaprojects

Another unique aspect of this project is its size and scope. Attorneys say only so many major construction players have the resources to take on these types of megaprojects. Of those, some may choose not to bid at all.

That was the case with the Purple Line's second round RFP, where three groups were short listed to bid, but only two – the winning Dragados-OHL team and a joint venture from Tutor Perini/Lunda – actually submitted proposals. A third team, Halmar International, opted not to move forward.

That limited market factors into how much leverage the government owner entity has on these jobs. For example, Ron Perini, Tutor Perini's CEO, made it clear on the firm's latest earnings call that he'd rather bid high on a mega contract and lose than underbid it and own the risk at a lower margin. 

"If we're going to add $5 billion or $6 billion worth of civil columbus oh dump truck company to our backlog and it takes five to six years to build it, nothing would be more foolish than for us to cut our margins in order to acquire it," Tutor said. "It'd be exciting when you got it, and then you'd live with it for the next five, six years."

Granite Construction has also publicly stated that it has pivoted away from targeting megaprojects with budgets of more than $500 million.

Michael Subak
Courtesy of Troutman Pepper
 

"There have been some fairly public departures of the larger columbus oh dump truck company who have said projects of this magnitude are not consistent with their risk appetite," said Michael Subak, a partner in the Philadelphia office of Troutman Pepper. "It's no surprise that some are dropping out."

Indeed, Perini also made the point that the firm is usually one of only two or three bidders on major projects. Given that limited market, owners of major infrastructure projects often need to be more conciliatory in their dealings with contractors.

"If you're talking about someone building an apartment complex, there's lots of columbus oh dump truck company in most cities who can do that," said Himmelstein. "But if you're looking at infrastructure like an airport or light rail, there's not a ton of them out there."

For that reason, Heller said it's likely the Purple Line's more narrow agreement with MTS came at a price.

"It sounds like the municipality can take away the ability of the contractor to walk by paying them for it," Heller said.

That could also influence other mega projects in the future. 

"To the extent there's a lesson learned from this, the pendulum will swing as it relates to the risk profile that columbus oh dump truck company are willing to take," said Subak. "I think that'll be factored into the way in which the projects are structured." 

Resolution clause

Another aspect of the agreement is its modified dispute resolution clause, which "shortens, clarifies and streamlines the process," according to MDOT. A "short fuse" arbitration provision is often used for that purpose.

"The parties agree beforehand to use a reputable construction arbitrator to arbitrate the case in some shorter period of time, like 30 or 60 days," Himmelstein said. "The idea is you don't wait six months."

The more complex the project, the more likely setting up that type of dispute resolution structure beforehand can help keep it on track.

Trent Cotney
Courtesy of Adams and Reese LLP
 

"These projects absolutely end up taking on a life of their own, especially over long stretches," said Trent Cotney, a partner in the Tampa, Florida, office of Adams and Reese. Light rail is particularly challenging, he said, since it involves underground, horizontal and vertical construction.

From that perspective, the Purple Line project and contract, for all its twists and turns thus far, could serve as a model for complicated infrastructure projects going forward, he said.

"This one in particular is a great, textbook example of how things go wrong, and then hopefully how you correct them and get to the finish line," Cotney said.

The Dotted Line series is brought to you by AIA Contract Documents®, a recognized leader in design and construction contracts. To learn more about their 200+ contracts, and to access free resources, visit their website here. AIA Contract Documents has no influence over Construction Dive's coverage within the articles, and content does not reflect the views or opinions of The American Institute of Architects, AIA Contract Documents or its employees.

Construction Dive news delivered to your inbox

Get the free daily newsletter read by industry experts

  • view sample
  • view sample

Editors' picks

Keep up with the story. Subscribe to the Construction Dive free daily newsletter

  • view sample
  • view sample