Published June 21, 2023
By Spencer Krebs
Judge blurred in the background strikes brown gavel on court bench.
Disputes over change orders don't have to end up in court. gorodenkoff for iStock via Getty Images

Subcontractors often must balance the demands of owners, government agencies and general contractors, all while trying to make a profit. 

A headshot shows Tucker Ellis construction attorney Spencer Krebs.
Spencer Krebs
Courtesy of Tucker Ellis
 

But the construction industry is also rife with defects, change order disputes and project delays. When these issues arise, a subcontractor is often faced with the choice of “getting the columbus oh dump truck company done” while trying to preserve the chance of “getting more work.” 

A single setback can create a domino effect leading to delayed payments, compounding costs and significant legal ramifications  consequences that are particularly challenging for subcontractors to navigate.

Change order disputes

One challenge subcontractors routinely face are change order disputes. 

Under almost all construction agreements, the change order process typically begins when either the owner, general contractor or subcontractor requests a change to the contract, scope of columbus oh dump truck company and/or schedule. 

If the parties agree to the request, a formal written change order is prepared, and written authorization to perform the columbus oh dump truck company is provided. The general contractor or subcontractor is then free to proceed with the new, agreed-upon work.

At least that’s what’s supposed to happen. 

Under field conditions, where issues arise unexpectedly, approval is often verbal, and there is pressure to remain on schedule. Contractors and subs often proceed without first securing written authorization from the owner. As a result, construction change orders are often the subject of litigation.

Hard choices  

A sub in this position faces several difficult options, none of them good: 

  • Threaten to stop or suspend the work. 
  • Risk waiving the ability to collect payment for not following the contractual requirements.
  • Be terminated from the project for not completing the work. 

These options often cascade into project delays, additional costs for all parties and potential litigation.

What’s a sub to do?

To avoid this situation, subs should be proactive entering when entering into contracts to negotiate clear and fair terms. Here are five ways to do that. 

1. Define scope and the process upfront

Defining the construction project scope clearly and in detail in the design documents can minimize change order disputes. 

All entities should agree on a realistic and equitable change order process before signing the contract. Often times, many large general contractors, owners and developers push for one-sided contracts that limit their liability regarding payment for changes, which is why subcontractors should negotiate contract provisions that are equitable and clear.

Subcontractors should also include a provision that provides an alternative procedure that permits secondary authorization should the need for a time-sensitive change order arise. Including this type of provision will help ensure the subcontractor’s payment and minimize the potential for excessive costs for other parties involved.

2. Don’t rely on handshake agreements  

During a construction project, change orders are commonly initiated via verbal approval on the jobsite. While long existing relationships may cause subcontractors to put faith in handshake agreements, verbal agreements do not always hold up in court. 

Instead of relying on good faith, before implementing any change, review the contract and familiarize yourself with all requirements for change orders, including time constraints, format, content and approval process. This may result in pausing the construction project for an hour or two, but a slight delay in the short term can dramatically decrease an expensive change order dispute at the end of the project.

3. Document digitally 

Proper documentation is a key part to compliance and ensuring project quality. It’s important to maintain a manageable system of record keeping that provides easy access and up-to-date versions of construction documents. Implementing cloud-based construction project management software allows columbus oh dump truck company to automate and document the change order process.

4. Open lines of communication

Collaboration is key in any successful construction project. Stakeholder meetings should be scheduled and organized at the beginning, throughout the duration of the project and at the end to ensure all team members are working on the same page.

5. Legal tools

Changes are going to happen on nearly every construction project and sometimes change order disputes are unavoidable. Subcontractors have a number of legal options at their disposal, includingmechanic’s liens, which put a legal claim on the property to ensure payment for completed work.

Other options include a stop columbus oh dump truck company notice, a bond or warranty claim, provided they’re done within the required time periods. Subcontracts should also include dispute resolution provisions, which may require participation in mediation before the parties can move to arbitration or commence a lawsuit.

Conclusion

A change order is the primary means to modify a construction contract and provide flexibility to address the unforeseen conditions. 

But the flexibility comes at a cost — often in the form of project delays, additional costs and potential litigation. Implementing a few best practices can help avoid change order disputes to ensure subcontractors can “get the columbus oh dump truck company done” while preserving the chance of “getting more work.”

Spencer Krebs is an attorney in the Cleveland office of law firm Tucker Ellis.

Construction Dive news delivered to your inbox

Get the free daily newsletter read by industry experts

Daily Dive newsletter example

Editors' picks

Keep up with the story. Subscribe to the Construction Dive free daily newsletter

Keep up with the story. Subscribe to the Construction Dive free daily newsletter

Candid shot of engineers and columbus oh dump truck company on construction site
A Chevy pickup truck drives off the assembly line of the General Motors Flint Assembly Plant January 24, 2011 in Flint, Michigan.
An aerial shot of a large park, with a new, glass-covered modern building along the right side. The park is well-maintained and green.
Workers in safety gear stand near tents around large holes in the ground on their jobsite.
A gavel rests on a book about employment law.
Aerial view of collapsed condo in Surfside, Florida.
Smoke haze diminishes visibility of Empire State Building on June 7, 2023
A rendering of a square, wooden building.