A rendering of the exterior of a stadium by a park.
A rendering of the $117-million CPKC Stadium, future home of the Kansas City Current under construction from J.E. Dunn and women-owned Monarch Build. Courtesy of CNW Group/CPKC
This audio is auto-generated. Please let us know if you have feedback.

Sports venues look different today. The updated, ideal fan experience influences design, as teams compete with high definition broadcasting to make an expensive outing to a game worth it.

As a result, builders’ columbus oh dump truck company on stadiums often revolves around installing massive screens, providing premium seating and creating comfort and ease for those in attendance — be that in their seats or exploring the concourse and surrounding area.

Here is a look at some of the major league sports arenas that showcase the trend and are scheduled to reach the finish line in 2024.

Intuit Dome

Location: Inglewood, California
Contractor: AECOM Hunt/Turner
Cost: $2 billion

A rendering of the Intuit Dome basketball arena in Los Angeles.
The Intuit Dome will become one of the most expensive sports venues ever built.
Courtesy of Los Angeles Clippers
 

When the 2024-25 NBA season begins, the Los Angeles Clippers will depart from Crypto.com Arena (formerly the Staples Center, which they currently share with the Lakers, their hometown rivals) for their own court. That means AECOM Hunt and Turner will need to deliver the project by the fall of this year.

The joint venture began pouring the $2 billion Intuit Dome’s foundation in January 2022 and finished its concrete frame six months later. When completed later this year, the stadium’s amenities will include nearly 18,000 seats, five basketball courts, a 38,375-square-foot Halo Board display, more than 120 restrooms and over 300 electric vehicle charging stations. 

One of the most expensive venues ever built, the Intuit Dome will create over 7,000 construction jobs over the course of its project lifecycle, according to a Clippers fact sheet.

The project also seeks a LEED Platinum certification, the highest available, according to AECOM’s website. The project team claims the stadium will operate 100% carbon free from opening. 

Scotiabank Arena

Location: Toronto
Contractor: PCL Construction
Cost: $350 million

The interior of a high end sports lounge at a stadium.
The Mastercard Lounge, one of the premium spaces renovated by PCL last summer.
Courtesy of PCL Construction
 

In the fall of 2023, Maple Leaf Sports & Entertainment announced the $350 million Scotiabank Arena Venue Reimagination project, a multi-phase renovation at the home of the NHL’s Toronto Maple Leafs and the NBA’s Toronto Raptors.

Last summer, the project team renovated and upgraded premium spaces on the 200 level and added new technology to concessions — including artificial intelligence technology for purchasing items without waiting in line. 

When the home teams’ current seasons end, PCL will begin “an all-encompassing design makeover of the 100 Level concourse,” according to the release. 

Upgrades before the teams’ regular seasons resume this fall will include modernized, grab-and-go style concession kiosks; an additional store; a redesigned broadcast studio and a new Tunnel Club on the Event Level, with up-close views of players entering the bowl from the locker room. 

Rogers Centre renovation

Location: Toronto
Contractor: PCL Construction
Cost: $300 million

Cranes and machinery move materials in the central bowl of a professional ballpark.
PCL began structural demolition of the Rogers Centre's central bowl in the fall.
Courtesy of PCL Construction
 

PCL Construction is keeping busy in its home country. For the last two offseasons, the contractor has performed substantial renovations at the 34-year-old home of MLB’s Toronto Blue Jays.

The contractor completed columbus oh dump truck company on the Rogers Centre’s first phase in April 2023, included a new weight room, staff locker room, more social spaces and patios and seat replacements.

Since last fall, the Edmonton, Alberta-based contractor has labored on the second phase of the project, due by opening day on April 11, 2024. It’s been a heavier lift this time around, as the project team reconfigures the 100 level seating area near the field from foul pole to foul pole. 

New columbus oh dump truck company includes the addition of three premium clubs near home plate and improved armrests and cup holders throughout the stadium.

Structural demolition of the stadium’s lower bowl took place in October, according to PCL, which saw the removal and recycling of 29.5 million pounds of concrete and steel in 13 days. Field-level excavations to create below ground space for new player facilities and premium clubs followed — which meant removing 780 truckloads of material and bringing in 530. 

The contractor installed a temporary bridge over the site of the former seating bowl to help facilitate the excavation.

CPKC Stadium

Location: Kansas City, Missouri
Contractor: J.E. Dunn/Monarch Build
Cost: $117 million

A rendering of the exterior of a stadium by a park.
When complete, CPKC Stadium will become the first venue constructed solely for a professional women's sports team.
Courtesy of CNW Group/CPKC
 

The future home of the Kansas City Current, part of the National Women’s Soccer League, will become the first stadium constructed solely for women’s sports, according to the team.

The $117-million CPKC Stadium has targeted an opening date for the 2024 season, set to begin this spring. Kansas City contractor J.E. Dunn and Overland Park, Kansas-based, women-owned Monarch Build are building the project, along with a female-led team at Lenexa, Kansas-based Henderson Engineers.

When the project team completes the stadium at the Berkley Riverfront Park jobsite, the stadium will hold 11,500 seats across general admission, club and suite levels, with all seats within 100 feet of the field.

Crypto.com Arena

Location: Los Angeles
Contractor: PCL Construction
Cost: Undisclosed

An interior rendering of a professional basketball court.
Crypto.com Arena's renovations this summer will see new additions and upgrades to suites and the main concourse.
Courtesy of AEG Worldwide
 

As the Clippers prepare to leave the venue they share with the Los Angeles Lakers — as well as the NHL’s Los Angeles Kings and the WNBA’s Los Angeles Sparks — Crypto.com Arena will also get a facelift.

PCL, the original builder of the venue in 1999, signed on in the summer of 2022 to upgrade Crypto.com Arena every offseason since. That year, the contractor installed two new LED screens and ribbon boards for the upper and lower bowl seating areas, and also redesigned the bar and grill in the main concourse and expanded the Chairman’s Club, according to the stadium’s website.

Last summer, the contractor added Terrace Suites: premium seats with a close view of the action. PCL also renovated the surrounding area to create one large plaza connecting the arena and L.A. Live for larger event programming. 

Finally, this summer will target more renovations and upgrades to the main concourse, tunnel club level renovations and newly reimagined locker rooms for the Kings, Lakers and Sparks.

Construction Dive news delivered to your inbox

Get the free daily newsletter read by industry experts

Daily Dive newsletter example

Editors' picks

Keep up with the story. Subscribe to the Construction Dive free daily newsletter

Keep up with the story. Subscribe to the Construction Dive free daily newsletter

Aerial view of the new computer chip factory that's being built by The Taiwan Semiconductor Manufacturing Company in Arizona on the North side of Phoenix.
JPMorgan Chase sign in front of building in street level view.
Waterfront view of a long open metal bridge.
An aerial view of a hospital tower where construction is almost complete.
Aerial shot of TSMC's $40 billion construction project in Phoenix, Arizona
A wide angle photo shows road widening construction columbus oh dump truck company underway in Tucson, Arizona.
Three construction workers stand in a tunnel, silhouetted in shadow.
The front of a theater lights up in the darkness. The red contrasts with the colors of a city at night.